| Milestone | Name | WPS | Lead Partners
| Project Month
| Delivery Date
| Comments | Status | | M2.1 | Website and collaborative web tools operational
| WP2
| INFN | M02
| 30/04/2009
| This milestone will be reached with the reation of the project website and of the other web-based collaborative tools | TBD
| M3.1
| Training material repository operational
| WP3
| COMETA
| M02
| 30/04/2009
| This milestone will be reached with the creation and filling of the website hosting the training material | TBD | M1.1
| Successful submission of first year deliverables
| WP1 | COMETA | M12 | 28/02/2010 | This milestone will be reached with the release of deliverable D1.1. | TBD | M3.2
| First year schools and workshops successfully
| WP2-WP3 | INFN-COMETA | M12 | 28/02/2010 | This milestone will be reached with the release of deliverables D2.2 and D3.2. | TBD | | M1.2 | Successful submission of second year deliverables | WP1 | COMETA | M24 | 28/02/2011 | This milestone will be reached with the release of deliverable D1.2 | TBD | | M3.3 | Second year schools and workshops successfully done
| WP2-WP3
| INFN-COMETA
| M24 | 28/02/2011 | This milestone will be reached with the release of deliverables D2.3 and D3.3. | TBD | | M1.3 | Successful submission of second year deliverables | WP1 | COMETA | M36 | 29/02/2012 | This milestone will be reached with the release of deliverable D1.3 | TBD | | M3.4 | Third year schools and workshops successfully
| WP2-WP3
| INFN-COMETA
| M36 | 29/02/2012 | This milestone will be reached with the release of deliverables D2.4 and D3.4. | TBD | M1.4
| Successful submission of fourth year deliverables | WP1 | COMETA | M48 | 28/02/2013 | This milestone will be reached with the release of deliverable D1.4. | TBD | M3.5
| Fourth year schools and workshops successfully done | WP2-WP3
| INFN-CATANIA
| M48 | 28/02/2013 | This milestone will be reached with the release of deliverables D2.5 and D3.5. | TBD |
|
|